Assignment 6 - Make Reports for Project Manager, Subcontractors and Owner
- Due Oct 22, 2018 by 11:59pm
- Points 30
- Submitting on paper
- Available Oct 8, 2018 at 12am - Nov 30, 2018 at 11:59pm
Assignment 6 - Make Reports for Project Manager, Subcontractors and Owner
change this assignment to this handout Download this handout:
Use the Logic Diagram that we have been creating as a class.
Each student will submit their own charts for this assignment.
1. Complete bar charts for
- Project Manager
- Subcontractors
- Owner
2. Complete Tabular Reports for
- Project Manager
- Subcontractors
- Owner
Use November 1 as start date to figure holidays. Make two rows at the top, one with the work day number, and one with the actual dates.
Name the project name with your name: i.e. Home for John Smith
Extra credit for assignments completed on the computer using a computer spreadsheet.
Why the computer is easier:
You can create one master spreadsheet with the job information; activity names and duration on the left column; the work day number and actual dates along the top. Then use the master to create the 3 types of bar and tab reports. (save each with their own file name as you create them, preserving the master)
Be sure to back up your files. (a quick way to back up is to email it to yourself as an attachment)